Employer : ExportEmployer's field of activity : IT & TechnologyProject size : InternationalManpower : 25Data center type :Edge data center, TOD Data CenterLocation :IraqProject status : Finished

Introduction

The TOD container data center project of IsIran Company, which is another export project of Abgine Pardaz Shargh abroad, was designed and built in 2018 and put into operation in 1401. This tactical data center was built according to the highest international standards. done to achieve satisfaction with the employer’s business.

Question

The concern of creating information security and providing a suitable environment for its safe transfer is a global concern and not only for Iranian companies and institutions. The TOD smart box export project responds to the following issues by satisfying the customer’s needs:

The need for more space to store the organization’s data
Increase the information security of the organization.
Integrated access to information by all members of the organization.
AND…

Project implementation challenges

There are always various challenges that builders face in designing, implementing and commissioning data centers and to solve them you need to have sufficient knowledge and information, experience and the art of handling the challenges. This project is no exception to this rule and the Abgine Pardaz Shargh team faced many challenges in the design, implementation and launch process.

Currency price fluctuations and changes in the parts purchasing process.
Changes to the customer order during the project.
The need to be flexible in decision making
The challenges of traveling and the problems associated with obtaining permission to cross roads
Organizations’ inconsistencies in the data center relocation process
Slow progress of the project due to subsequent official holidays

Despite such challenges, in line with the commitments made to the employer, Abgineh Pardaz Shargh delivered the data center as they wanted and successfully launched it so that the satisfaction of the group and the priorities of the organization were fully met.

The suggested solutions

Without a doubt, challenges cannot be controlled without using experience and the art of management, and this is the one thing that cannot be studied in any scientific book or article. This is exactly the same technique used by the APS team to address the issues of each project.

Implementation stages of project

  • 1-جلسات با کارفرما و بررسی نیازها

    2-ارائه پیشنهادات و بررسی آن‌ها توسط کارفرما

    3-بررسی فضا و امکانات کارفرما

    4- شروع پروژه

  • 1-ارائه طراحی مرکز داده و تایید طرح توسط کارفرما

    2-تامین و ساخت قطعات و تجهیزات

    3-نصب تجهیزات داخل کانتینر

  • 1-ارائه طراحی مرکز داده و تایید طرح توسط کارفرما

    2-تامین و ساخت قطعات و تجهیزات

    3-نصب تجیزات داخل کانتینر

  • 1-راه‌اندازی و تست اولیه دیتاسنتر

    2-کنترل کیفیت مرکز داده Quality Control

    3-تست فول‌لود Full Load دیتاسنتر

  • 1-بررسی عملکرد صحیح دیتاسنتر

    2-تحویل موقت به کارفرما

    3-تست نهایی پروژه در محل استقرار

  • 1-آموزش به کارفرما

    2-تحویل دائم به کارفرما

    3-اتمام پروژه 

Project implementation achievements

Perhaps the most important result of each of the projects is the creation of a data center using the most modern technological methods in the world, which meets all the needs of the employer established in the contract.

Behzad Borhani / CEO of APS